Welcome to our Help Page. Search for answers using the search box below or select the appropriate category listed on the page,if you are unable to find your answer please reach out to us at info@ecommconstruction.com and one of our support team members will be in touch with you.
Popular searches: Submittal, Reset Password, Add a User, RFI, Change Order
How to Manage Plans, Specifications & Addenda in eComm
Managing construction drawings, specifications, and addenda is an important part of keeping project information organized and accessible. eComm Construction Information Management provides tools for uploading, organizing, reviewing, publishing, and maintaining these documents throughout the life of a construction project.
The enhanced Plans, Specifications, and Addenda features introduce Plan Sets, Volumes, automatic drawing recognition, bulk assignments, drawing versioning, and improved document upload workflows.
This guide explains how to use these features to organize project documents, upload new drawings, manage revisions, and maintain accurate project records.
1. Access Plans, Specifications, and Addenda
Before uploading documents, open the appropriate area within your eComm project.
Step 1: Log in to your eComm account.
Step 2: Open the project where you want to manage documents.
Step 3: Navigate to the Plans, Specifications, or Addenda area of the project.
Step 4: Select the appropriate document area based on the files you need to upload or manage.
Each area provides tools for organizing and managing its corresponding documents.
2. Understand Plan Sets
Plan Sets allow projects to maintain separate collections of drawings within the same project.
This is especially useful for projects involving multiple buildings, facilities, or construction scopes that may use identical Plan Numbers.
Example: Multiple Buildings
Imagine a school construction project containing an elementary school and a junior/senior high school.
Both buildings may have a drawing numbered A101.
By creating separate Plan Sets for each building, eComm can maintain the drawings independently.
Elementary School: A101 – Floor Plan
Junior/Senior High School: A101 – Floor Plan
Although both drawings share the same Plan Number, each belongs to a different Plan Set and maintains its own revision history.
3. Create and Manage Plan Sets
Projects begin with a default Plan Set. For standard projects, you can continue using the default without creating additional sets.
If your project requires separate drawing collections, additional Plan Sets can be created.
Steps
Step 1: Open the Plans area of your project.
Step 2: Locate the Plan Set management options.
Step 3: Choose the option to create a new Plan Set.
Step 4: Enter a descriptive name for the Plan Set.
Step 5: Save the new Plan Set.
Step 6: Repeat the process for additional buildings or drawing collections when necessary.
Recommended Plan Set Names
“Elementary School”
“Junior/Senior High School”
“Administration Building”
“Parking Garage”
Tip: Only create additional Plan Sets when your project requires independent drawing collections. Most projects can use the default Plan Set.
4. Organize Plans Using Volumes
Volumes provide another level of organization within each Plan Set.
They are useful when drawing packages are delivered in multiple volumes or need to be separated into smaller groups.
Steps
Step 1: Open the Plans area.
Step 2: Select the appropriate Plan Set.
Step 3: Locate the Volume management options.
Step 4: Create a new Volume.
Step 5: Enter a name for the Volume.
Step 6: Save the Volume.
Volumes can also be renamed and managed as the project evolves.
Example Volume Organization
“Volume 1 – General and Architectural”
“Volume 2 – Structural”
“Volume 3 – Mechanical and Electrical”
Tip: Volumes are optional. Create additional Volumes when they make large drawing packages easier to organize and navigate.
5. Upload New Plans
The redesigned Plan upload process allows users to upload multiple PDF files, review drawing information, and organize Plans before completing the upload.
Steps
Step 1: Open the Plans area of your project.
Step 2: Begin a new Plan upload.
Step 3: Select the PDF files you want to upload. You can select multiple files or use the drag-and-drop upload area.
Step 4: Allow eComm to process the uploaded files.
Step 5: Review the Plan information identified during processing.
Step 6: Make any necessary corrections or assignments.
Step 7: Follow the remaining upload and review steps to complete the process.
For larger files, eComm displays processing feedback while the PDFs are being prepared.
Important: Keep your browser window open until the upload processing is complete.
6. Review Automatically Recognized Plan Numbers and Names
During the upload process, eComm analyzes drawings to identify Plan Numbers and Plan Names.
This helps reduce manual data entry when uploading large drawing packages.
Because drawing layouts can vary, users should review the identified information before completing the upload.
Steps
Step 1: Upload your drawing PDF files.
Step 2: Allow eComm to process and analyze the drawings.
Step 3: Review the Plan Numbers identified by eComm.
Step 4: Review the associated Plan Names.
Step 5: Correct any information that was not recognized accurately.
Step 6: Continue once the drawing information has been reviewed.
Example
Plan Number: A101
Plan Name: First Floor Plan
Plan Number: S201
Plan Name: Foundation Details
Tip: Pay particular attention to Plan Numbers when uploading revisions. eComm uses matching Plan Numbers within a Plan Set to determine whether a drawing is a new Plan or a new version of an existing Plan.
7. Assign Disciplines to Plans
Disciplines help organize construction drawings according to their area of work.
This makes it easier for project teams to locate drawings within large drawing packages.
Common Disciplines
Architectural
Structural
Civil
Mechanical
Electrical
Plumbing
Steps
Step 1: During the Plan upload process, locate the Discipline assignment options.
Step 2: Select the drawing or drawings you want to categorize.
Step 3: Choose the appropriate Discipline.
Step 4: Review the assignments.
Step 5: Continue the upload process.
Tip: Consistent Discipline assignments make drawing packages easier to navigate and review.
8. Organize Plans Using Tags
Tags provide an additional way to organize Plans beyond Plan Sets, Volumes, and Disciplines.
Tags are optional and can be customized based on the needs of your project.
Steps
Step 1: Open the Plan upload or management area.
Step 2: Locate the Tags option.
Step 3: Select an existing Tag or create a new Tag as needed.
Step 4: Assign the Tag to the appropriate Plans.
Step 5: Save or continue the upload process.
Example Tags
“Building A”
“Renovation”
“Site Improvements”
“Phase 2”
These are examples of project-specific organizational labels rather than required Tag names.
9. Use Bulk Assignment for Multiple Plans
Bulk assignment allows users to update multiple Plans at the same time instead of editing each drawing individually.
During Plan upload, bulk assignment can be used for Plan Sets, Volumes, Disciplines, and Tags.
Steps
Step 1: Upload your drawing files.
Step 2: Navigate to the Plan review and assignment area.
Step 3: Select the Plans that require the same assignment.
Step 4: Choose the bulk assignment option for the information you want to update.
Step 5: Select the desired Plan Set, Volume, Discipline, or Tags.
Step 6: Apply the changes to the selected Plans.
Step 7: Review the updated information before completing the upload.
Example
If you are uploading 30 mechanical drawings, you can select those drawings and assign the Mechanical Discipline together rather than updating each drawing separately.
Tip: Bulk assignment is especially useful when processing large drawing packages with common organizational requirements.
10. Review and Sort Plans
eComm organizes Plans according to the established Index Page order.
Users can temporarily sort Plans when reviewing information and return to the established drawing order when needed.
Steps
Step 1: Open the Plans area.
Step 2: Review the displayed Plans.
Step 3: Apply an available sorting option when needed.
Step 4: Review the drawings in the selected order.
Step 5: Select Reset Sort Order to return to the established drawing order.
This allows users to review drawings in different ways without permanently changing the established Index Page order.
11. Upload Revised Plans
eComm provides Plan versioning to help project teams manage drawing revisions throughout the project.
When updated drawings are uploaded, eComm compares their Plan Numbers with existing drawings within the selected Plan Set.
If a Plan Number matches an existing drawing within that Plan Set, the uploaded drawing is treated as a new version of that Plan.
If the Plan Number does not already exist, the drawing is added as a new Plan.
Steps
Step 1: Open the Plans area.
Step 2: Select the Plan Set containing the drawings being revised.
Step 3: Begin a new Plan upload.
Step 4: Select the revised PDF drawings.
Step 5: Enter or select an appropriate Version name for the upload.
Step 6: Allow eComm to process the files.
Step 7: Review the recognized Plan Numbers and Plan Names.
Step 8: Verify that revised drawings are associated with the correct existing Plans.
Step 9: Complete the upload and applicable publication steps.
Example Version Names
“Bid Set”
“Issued for Construction”
“Revision 1”
“Revision 2”
Important: Always select the correct Plan Set when uploading revisions. The same Plan Number can exist in multiple Plan Sets, each with its own revision history.
12. Review Previous Plan Versions
eComm maintains revision history for individual Plans, allowing project teams to access previous versions when needed.
Steps
Step 1: Open the Plans area.
Step 2: Navigate to the appropriate Plan Set.
Step 3: Locate the Plan you want to review.
Step 4: Open the Plan’s available version history.
Step 5: Select the previous version you want to review.
This helps maintain access to historical drawing information while keeping the latest version available for current project use.
Tip: Confirm which revision is current before using a drawing for construction coordination or other project activities.
13. Review Plan Releases
The Releases area provides a record of Plan uploads and publishing activity.
Releases help project teams review which drawing packages have been uploaded, their associated Version information, and their publication status.
Steps
Step 1: Open the Plans area.
Step 2: Navigate to Releases.
Step 3: Review the available Releases.
Step 4: Locate the Release you want to inspect.
Step 5: Review its Version name, number of Plans, and upload status.
Step 6: If an upload is ready for review, open it and continue the applicable review process.
Step 7: For a published Release, open its associated Plans as needed.
Releases provide an organized way to review drawing upload history and publishing activity.
14. Upload Project Specifications
The Specifications area provides an updated process for uploading and organizing specification documents.
Users can upload multiple PDF files during the same upload workflow.
Steps
Step 1: Open the Specifications area of your project.
Step 2: Begin a new Specification upload.
Step 3: Select the PDF files you want to upload.
Step 4: Add multiple files when needed.
Step 5: Allow eComm to process the files.
Step 6: Review the document information during the guided upload process.
Step 7: Complete the Specification upload.
The updated workflow reduces the need to start a separate upload for every Specification PDF.
15. Organize Specifications Using Volumes
Specification Volumes help organize project manuals that are delivered in multiple sections or separate PDF packages.
Steps
Step 1: Open the Specifications area.
Step 2: Locate the Volume management options.
Step 3: Create an additional Volume when needed.
Step 4: Enter the Volume name.
Step 5: Save the Volume.
Step 6: Organize the corresponding Specification documents within the appropriate Volume.
Example Volume Names
“Volume 1”
“Volume 2”
“Volume 3”
Volumes can be renamed and managed as project requirements change.
16. Upload Project Addenda
The Addenda area provides a document-management experience consistent with the updated Plans and Specifications features.
Users can upload multiple Addenda PDFs together and organize them into Volumes when additional grouping is needed.
Steps
Step 1: Open the Addenda area of your project.
Step 2: Begin a new Addenda upload.
Step 3: Select the Addenda PDF files.
Step 4: Add multiple files when applicable.
Step 5: Allow eComm to process the uploaded documents.
Step 6: Review the document information.
Step 7: Complete the guided upload process.
Tip: When uploading multiple Addenda files, review the selected documents before completing the upload to ensure the correct documents are included.
17. Organize Addenda Using Volumes
Volumes can also be used within Addenda when a project requires additional document organization.
Steps
Step 1: Navigate to the Addenda area.
Step 2: Locate the Volume management options.
Step 3: Create a Volume if additional grouping is needed.
Step 4: Enter a descriptive Volume name.
Step 5: Save the Volume.
Step 6: Organize the applicable Addenda documents within that Volume.
Use additional Volumes only when they help make the project’s Addenda easier to manage.
18. Use Drag-and-Drop Document Uploads
The updated upload experience supports drag-and-drop file selection across Plans, Specifications, and Addenda.
Steps
Step 1: Open the appropriate document area.
Step 2: Start a new upload.
Step 3: Locate the files on your computer.
Step 4: Drag the selected PDF files into the upload area.
Step 5: Confirm that the files have been added.
Step 6: Allow eComm to complete the processing step.
Step 7: Continue reviewing the uploaded documents.
eComm provides clearer visual feedback when files are dropped and improved processing messages for larger PDF files.
Important: Do not close the browser window while files are still processing.
19. Access the Archive Bin
The Archive Bin provides access to archived documents when they need to be reviewed.
Steps
Step 1: Open the relevant document management area.
Step 2: Navigate to the Archive Bin.
Step 3: Review the archived documents.
Step 4: Open the document you need to reference.
The Archive Bin provides a way to locate archived information without including those documents in the primary active document view.
20. Manage Document Settings
Depending on the document type, project administrators can manage the organizational settings used by Plans, Specifications, and Addenda.
These settings may include Plan Sets, Volumes, Disciplines, and Tags.
Steps
Step 1: Open the appropriate document area.
Step 2: Access the available management or settings options.
Step 3: Select the organizational setting you want to update.
Step 4: Create, rename, or manage the available organizational entries as needed.
Step 5: Save the changes.
Breadcrumb navigation also helps users identify their location when moving between Plan Sets, Volumes, Releases, and document views.
Best Practices for Managing Plans, Specifications, and Addenda
Use Plan Sets Only When Needed
For most projects, the default Plan Set is sufficient. Create additional Plan Sets when independent drawing collections may contain duplicate Plan Numbers.
Review Drawing Recognition Results
Always review automatically identified Plan Numbers and Plan Names before completing an upload. Accurate information is especially important for managing future revisions.
Organize Documents Consistently
Use consistent Volume names, Discipline assignments, and Tags so project documents remain easy to navigate.
Use Bulk Assignment for Large Uploads
When several Plans require the same organizational information, use bulk assignment rather than editing each drawing separately.
Choose the Correct Plan Set for Revisions
Plan versions are matched within the selected Plan Set. Selecting the wrong Plan Set can prevent an uploaded revision from being associated with the intended existing drawing.
Use Descriptive Version Names
Version names such as “Bid Set,” “Issued for Construction,” and “Revision 1” can help project teams understand the purpose of a drawing upload.
Review Releases
Use Releases to review drawing upload activity, publication status, and associated Plan versions.
Verify Documents Before Completing Uploads
Check that the correct PDFs, Plan Numbers, Plan Names, and organizational assignments are included before completing each upload.
Allow Large PDFs to Finish Processing
Large drawing and specification packages may require additional processing time. Keep the browser window open until eComm indicates that processing is complete.
Frequently Asked Questions
Do I need to create a Plan Set for every project?
No. Projects can continue using the default Plan Set. Additional Plan Sets are useful when separate buildings or drawing collections may use the same Plan Numbers.
Can two drawings have the same Plan Number?
Yes. Drawings can share the same Plan Number when they belong to different Plan Sets. Each drawing maintains its own revision history.
Can I upload multiple PDF files at once?
Yes. The updated upload experience supports multiple PDF uploads across Plans, Specifications, and Addenda.
Does eComm automatically identify Plan Numbers?
Yes. eComm analyzes uploaded drawings to identify Plan Numbers and Plan Names. Users should review and correct the information when necessary.
What happens when I upload a revised drawing?
eComm compares the drawing’s Plan Number with existing drawings in the selected Plan Set. Matching Plan Numbers are treated as new versions, while new Plan Numbers are added as new Plans.
Can I access previous drawing versions?
Yes. eComm maintains a revision history for individual Plans and allows users to access previous versions when needed.
Can I organize Specifications into Volumes?
Yes. Specification Volumes can be created and renamed to support project manuals delivered in multiple volumes.
Can Addenda be uploaded together?
Yes. Multiple Addenda PDFs can be uploaded during the same upload workflow.
What is the Releases area used for?
Releases provides information about Plan uploads and publishing activity, including associated Versions, Plan counts, and upload statuses.
Do I need to change my existing project setup?
For most projects, no special setup is required. The default Plan Set remains available, and additional organizational features can be used when needed.
Conclusion
The enhanced Plans, Specifications, and Addenda features in eComm provide improved tools for organizing, uploading, reviewing, and managing construction project documents.
With Plan Sets, Volumes, automatic drawing recognition, bulk assignments, drawing versioning, and Releases, project teams can more easily manage large drawing packages and maintain access to previous revisions.
The updated Specifications and Addenda workflows also make uploading and organizing multiple documents more efficient.
By using these features consistently, project teams can maintain organized construction records and make important documents easier to locate throughout the project.
Learn more about the update: Plans, Specifications & Addenda Enhancements.
Watch the feature demonstration: eComm Plans & Specifications Update Video.
Learn more about eComm Construction Information Management at ecommconstruction.com.